Seattle’s new billing system for its public-utilities customers will launch a year or more behind schedule and cost at least $34 million more than initially projected. The project to build a new ...
The system was 11 months late and about $43 million over budget when it launched last year due to “an unrealistic initial schedule, additions to the scope, project staff who were challenged by ...